Emergency Department Project Updates
December CONSTRUCTION UPDATE:
-
Fireproofing and Roofing - Gravel Stops
- Fascia
- Ambulance & Covered Walkway Roofing
- CMU, Siding, and Windows
- Building Expansion Joints
- Fiber Cement Panels
- Penthouse Metal Panels
Interior Build-Out- Penthouse
- CT & RAD Room
- Drywall and Taping
- Controls
- Painting
- Trim
- Tiling
- Ceiling Grid
- Bathroom Fixtures
- Lighting
Site Work- Utility Yard and Fuel Tank
- Side Walks
- Curbs
- Pneumatic Tube & DAS Conduit Installation in Existing Back Corridor
- Switch Gear for ED Power
November CONSTRUCTION UPDATE:
- Exterior siding rough-in underway
- Roofing of covered walkway and ambulance port underway
- Roofing set for completion
- Penthouse build-out underway
- Gypsum wall board installation underway
- Site work:
- Fuel tank installation underway
- Curb and trench work underway
- Window siding installation underway
- Interior build-out underway

- Insulation (thermal and sound)
- Wall rough-ins (plumbing, mechanical, and electrical)
- Controls
October CONSTRUCTION UPDATE:
- Roofing of ED underway
- Window framing and siding installation underway
- Interior build-out underway
- Insulation (piping, ductwork, thermal, and sound)
- Wall rough-ins (electrical plumbing, med gas, and plumbing)
- Fire sprinkler mains and branch lines
- Taping and caulking
- Interior framing

- Top down taping and caulking
- Site work underway
- Conduits for signage and lighting
- Irrigation sleeves
- Curbs
- Asphalt
Covington Emergency Department Milestone Reached
Signatures from MultiCare employees and City of Covington staff on the final steel support beam become part of MultiCare’s history
Hosted by Sellen Construction, the ceremony included the opportunity for MultiCare employees to sign the specially decorated red, white and blue beam. Covington Mayor Margaret Harto, City Manager Derek Matheson, Councilmember Wayne Snoey and other city staff also attended and signed the beam.
The beam will not be a visible part of the building once construction is complete, but the signatures will forever be part of the MultiCare Covington Emergency Department.


SEPTEMBER CONSTRUCTION UPDATE:
- Roof decking completed
- Exterior wall construction underway
- Asphalt demolition
- Structural steel work completed
- Fireproofing and roofing in progress
- Interior build out, wall and door framing, and roof drain installation in progress
June construction update:
Week of June 20, 2011:
Important tasks include:
- Utility installation ongoing and continuing through 7/8/11.
- Upcoming impacts include:
- Loss of 11 parking stalls for utility work 6/15-6/22/11.
Week of June 13, 2011:
- Rough Grading Continues: Leveling the site.
- Trench Digging Continues: Prepping for utility piping.
- Utility Piping Work to Begin: Installing piping for future utility lines.
Week of June 6, 2011:
- Construction: Continued removal of trees, demolition of asphalt and curbs, and start of rough grading.
- Jurisdictional: Waiting on Soos Creek Sewer Permit before construction can formally begin.
May construction update:
Week of May 31, 2011:
Environmental air testing and quality assurance will be performed to confirm air quality and effectiveness of the existing HVAC system and to put in place measures to ensure that the air within the building is not compromised by construction activities. Employees will be mostly unaware of this activity but may see a few people walking through their space. Demolition of asphalt and curb will also take place next week.
Week of May 23, 2011:
- Jack hammers and other equipment to arrive to prepare for noise testing and other site work on Tuesday.
- Continued marking of utility locations.
- Digging approximately 16 potholes to understand water levels on the property.
- Noise and Environmental Testing - tests are being performed to ensure that the imaging equipment will not be adversely affected by vibrations. Environmental testing is being performed to confirm air quality and effectiveness of the existing HVAC system.
- Tree removal – Trees marked with orange tags must be removed for site work to begin.
